Project Summary

Rothstone Estates in a JV with Peveril Securities have designed, developed and constructed a new 1,800 square foot standalone Costa Coffee drive thru plus 3 Zest EV spaces located on Barn Road, Congleton.

Key Features

Rothstone/Peveril agreed a 15 year lease with Costa and 30 years with EV.

Facts and Figures

  • Investment Value: £1.7m
  • Construction Duration: 21 weeks
  • Start Date: May 2024
  • Completion Date: September 2024
  • Architect: The Harris Partnership
  • Developer: Rothstone/Peveril
  • Structural Engineer: GSA
  • Contractor: Ellenby Construction
  • Investor/Purchaser: Private
  • Sale Completion: Due April 2025 5.56%NIY

Location

Costa
Congleton

Directions

Interested in working with us?

Get in touch